The Meadows Bardia | Construction Update

We are gladly to advise that The Meadows Bardia is on track for completion according to the latest estimated time frames:

Stage 1 

Lots 2 to 11

Rear retaining walls 100% complete

House frames are 100% complete

Lots 2/3/4/5/6 roof tiling progressing (photo attached)

Brickwork progressing

 

Note: the attached photos are now 21 days old so more has happened since then, new photos will be taken shortly.

 

Lots 12 to 21

Rear retaining walls now 100% complete

House frames are 100% complete

Lots 16/17 – roof tiling complete

Brickwork progressing

 

Stage 2

Civil construction is progressing well

Sewer and drainage is 100% complete

Kerb and gutter is 100% complete

Asphalt (final seal of road) to be completed by 1st of April (subject to weather)

House DA’s for Lots 24 to 37, 64 to 69 are now out of Council/ 38 to 63 – pending Council approval (next week or so)

 

Community Facilities

Construction has started

The main pool has been poured (photo attached)

Children’s play equipment, furniture and shelters have been ordered

Expected completion – July/ August

 

Some updated construction photos: